Advantages and Disadvantages of Piers on Screw Pile Foundations
Advantages:
• Ease of
Installation: Screw piles are easily installed in difficult soil conditions
without the need for heavy equipment.
•
Stability: The structure is resistant to fluctuating water levels and soil
changes.
•
Durability: With regular maintenance, the pier will last for many years.
•
Environmental Impact: The piles do not disrupt the water body's ecosystem.
Disadvantages:
• Cost of
Materials: The price of piles and other components can be quite high.
•
Installation Quality Requirements: Incorrect installation of piles can lead to
structural instability.
Required
Materials and Tools for Construction
• Screw
Piles: The foundation of the structure is selected based on the depth of the
water body and the soil type.
• Wooden
Beams: For creating the frame and decking.
• Metal
Fasteners: Bolts, anchors, and brackets for securing structural elements.
• Tools:
Shovels, hammers, level, drill, wrenches, and special tools for screwing in
piles.
Pier Accessories
For proper
and safe pier operation, it's important to include the following additional
elements:
•
Anti-corrosion coatings: All metal parts of the structure must be protected
from corrosion.
• Railings:
Installing railings will improve the safety of the pier.
• Floating
elements: For structures that require flexibility with changing water levels,
pontoons can be used.
Stages of Building a Pier on Screw Piles
You can
build a pier yourself by following these step-by-step instructions:
1. Site
Preparation
Before
construction, you must prepare the site for installing the piles. To do this,
you will need to:
• Level the
area near the water body and remove any uneven surfaces.
• Cover the
area with gravel or crushed stone to ensure a flat and stable surface.
2. Marking
the Pile Locations
Mark the
pile locations according to the pier design. To do this, use pegs and string to
mark the line and locations for installing the piles. The distance between the
piles must be uniform and in accordance with the design.
3.
Installing the Pile(s)
Installing
the screw piles is a key stage in pier construction. This requires:
• Screw the
screw piles into the ground manually or using specialized equipment.
• Check the
verticality of the piles using a spirit level.
• Screw the
piles until they reach solid ground or a layer with high bearing capacity.
• Trim the
piles to a uniform level using a grinder or hacksaw.
• Cover the
pile caps with special caps to protect them from moisture and debris.
4.
Installing the Grillage
The
grillage supports the pier decking and connects the piles together. To install
the grillage, you must:
• Assemble
the grillage from a metal profile or timber.
• Secure
the grillage to the piles with bolts.
5. Laying
the Decking
The pier
deck can be made of planks, decking, or other materials. To install the
decking, you need to:
• Lay the
decking on the foundation.
• Secure
the decking with brackets and screws.
6.
Installing Railings and Handrails
Railings
and handrails are important for the convenience and safety of the pier. To
install them, you need to:
• Install
the railings and handrails using special fasteners.
7. Wood
Protection
All wooden
pier elements must be treated with a preservative and coated with paint or
varnish to protect against moisture and insects.

Comments